Progress Update 11/23/10

Work continues at the modular factory. Five out of the 18 boxes are now in production, with three having walls up already. The boxes we posted photos of yesterday have been moved to the next station where they will get ceilings, plumbing and electrical fit outs. Here are a few photos of the work done on 11/23/10:

From Bancroft Green Photos
From Bancroft Green Photos
From Bancroft Green Photos
From Bancroft Green Photos